Spending APBN 38 Billion Building Roads, Flotim Regional Government Prepares 5 Hectare Huntap Location
REINHA.com – The construction of road access to permanent residential locations (Huntap) in Kuhe which is being carried out from the intersection of Pululera Village, Wulanggitang District, East Flores Regency (Flotim) costs 38.5 billion from the 2025 State Revenue and Expenditure Budget (APBN). for displaced residents affected by the eruption of Mount Lewotobi with an available area of 5 hectares.
Road access work to the Huntap Kuhe location based on information collected by the media,
carried out by PT Dewi Graha Indah, with a duration of 180 working days from the issuance of the Work Start Order (SPMK) dated 15 December 2025.
According to media monitoring, the 8,350 kilometer long road work requires 3 months of work time with only 1.5 kilometers of the field being worked on. Currently, the road work is still in the process of digging and filling, some of which are already covered with stone masonry.
Satker PJN wialyah IV/PPK 45 NTT Province, Victor A.Nalle, confirmed by the Media (Friday, 27/2/2026) is optimistic about the completion of the road work to the Huntap location.
“We are optimistic that the road work to Huntap Nobo Leto will be completed according to the time schedule,” said Victor Nalle.
Victor Nalle continued that rainfall conditions are an obstacle and the change of location from Noboleto to Kuhe means that the working time can be until August 2026.
Regarding road compaction, Victor Nalle said, for a length of 1.5 kilometers, after accumulating and compacting it is deemed sufficient, we will continue with aggregate.
“In April we will hot mix 1.5 kilometers,” said Victor Nalle optimistically.
Regarding the availability of 5 hectares of land in Kuhe for Huntap development, East Flores Regent Anton Doni Dihen told this media (Saturday, 28/2/2026) that he was focused on the availability of 5 hectares for Huntap.
“The potential for the Huntap Kuhe location can be increased to 20 hectares, but the Flotim Regional Government is focusing first on 5 hectares because with that size the land acquisition process is easier because above 5 hectares it needs to be delegated to the Provincial Government,” said Regent Anton Doni Dihen.
Regarding the increase in land area around Kuhe, continued Regent Antonius Doni Dihen, there was an offer of location to the East Flores Regional Government, but the Regional Government remains careful about mutual claims of land control which can cause land acquisition to fail, concluded Regent Anton Doni Dihen.**(BM)
Berita Terkini
Berita Terbaru
Daftar Terbaru
News
Jasa Impor China
Berita Terbaru
Flash News
RuangJP
Pemilu
Berita Terkini
Prediksi Bola
Technology
Otomotif
Berita Terbaru
Teknologi
Berita terkini
Berita Pemilu
Berita Teknologi
Hiburan
master Slote
Berita Terkini
Pendidikan
Resep
Jasa Backlink
Slot gacor terpercaya
Anime Batch
Comments are closed, but trackbacks and pingbacks are open.